PROJECT OVERVIEW
High-Rise Facade Remediation in Edgware
Centurion House is a high-rise residential building in Edgware where UKR Facades completed a £2.5m fire-safety remediation project to improve the safety and compliance of the external wall system. The works focused on replacing the existing insulated render with a new non-combustible insulation and render system.
The 42-week construction programme reached completion in July 2024. Located on a busy high street, the project required the facade works to be carefully coordinated around significant pedestrian and vehicular activity, while cafes, shops and a gym at ground level remained fully open throughout delivery.
Client
Confidential
Duration
42 Weeks
Value
£2.5M
Completion
July 2024
SCOPE OF WORKS
Insulated Render Replacement
The remediation package focused on the replacement of the building’s insulated render system. A new facade build-up incorporating Rockwool insulation and a VPI render finish was installed across the high-rise residential building as part of the fire-safety works.