PROJECT OVERVIEW
Fire-Safety Facade Upgrades to a High-Rise Hotel
A £650k programme of fire-safety remediation was delivered by UKR Facades at Leonardo Hotel Derby, addressing key elements of the high-rise building’s external wall system. Throughout the works, the city-centre hotel remained fully operational and at full occupancy.
Across 20 weeks, the project involved replacing insulated render, spandrel panels and fire barriers with new specified systems. The programme concluded in May 2025, with careful coordination of site activity helping the works progress safely and efficiently around hotel operations, guests and the constraints of the surrounding city-centre environment.
Client
Leonardo Hotels
Duration
20 Weeks
Value
£650K
Completion
May 2025
SCOPE OF WORKS
Upgrading the External Wall System
The remediation package focused on key elements of the hotel’s external wall build-up, replacing the existing insulated render, spandrel panels and fire barriers. New render, insulation and fire-barrier systems were installed as part of the works, with delivery coordinated around the continued operation of the hotel.