PROJECT OVERVIEW

Facade Remediation Across Three Residential Buildings

Lime Square is a £2.1m fire-safety remediation project spanning three mid-rise residential buildings in Newcastle. UKR Facades delivered a coordinated package of external works to improve fire safety and compliance across the development.

Completed in January 2026, the 35-week construction programme included the replacement of insulated render, timber decking and the flat roofing system. The buildings remained in full occupation throughout the works, requiring careful resident liaison and project planning to minimise disruption and maintain normal operations as much as possible.

Client

Confidential

Duration

35 Weeks

Value

£2.1M

Completion

January 2026

Refurbished facade between residential blocks at Lime Square in Newcastle

SCOPE OF WORKS

Integrated Facade, Decking & Roofing Works

The remediation project involved the replacement of insulated render, decking and the flat roofing system across three residential buildings. The works were undertaken within the constraints of the existing development, requiring careful planning and coordination to manage the practical and logistical challenges associated with construction in an occupied residential environment.

PermaRock Insulated Render
MyDek Aluminium Decking
Bauder Tapered Insulation Flat Roofing System

PLANNING & COORDINATION

Managing Remediation Around an Existing Development

Limited working space at Lime Square placed additional demands on the coordination of access, deliveries and site operations throughout the 35-week programme. Careful logistical planning helped the works progress efficiently across the three buildings despite the constraints of the site.

Resident liaison formed another important part of the delivery approach, with proactive communication helping to minimise disruption while remediation works progressed. By coordinating site activity around the existing development and its residents, the project was successfully delivered through to completion in January 2026.