PROJECT OVERVIEW
Facade Remediation Across Three Residential Buildings
Lime Square is a £2.1m fire-safety remediation project spanning three mid-rise residential buildings in Newcastle. UKR Facades delivered a coordinated package of external works to improve fire safety and compliance across the development.
Completed in January 2026, the 35-week construction programme included the replacement of insulated render, timber decking and the flat roofing system. The buildings remained in full occupation throughout the works, requiring careful resident liaison and project planning to minimise disruption and maintain normal operations as much as possible.
Client
Confidential
Duration
35 Weeks
Value
£2.1M
Completion
January 2026
SCOPE OF WORKS
Integrated Facade, Decking & Roofing Works
The remediation project involved the replacement of insulated render, decking and the flat roofing system across three residential buildings. The works were undertaken within the constraints of the existing development, requiring careful planning and coordination to manage the practical and logistical challenges associated with construction in an occupied residential environment.